City of Port Moody - Neighbourhood Energy Utility
November 16th, 2026
As mentioned in previous updates, on September 29, Council directed staff to cease further work regarding the Neighbourhood Energy Utility (NEU) in the short term, and to maintain requirements and covenants for developments within the Moody Centre TOD area to be NEU-ready and to connect to a future NEU (should one be built in the long term). The direction was based on conducted business case cost considerations, noting the potential cost impacts to developers.Â
 Â
More information can be found in the full report by City staff.Â
Â
September 30th, 2025
At the Regular Council Meeting on September 16, staff provided an update on the Neighbourhood Energy Utility Preliminary Design Report. Council endorsed the report and the following next steps:Â
- Report back to Council in fall 2025 with the completed business case, including user rate analysis, capital structure, and cost allocation and recovery.
- Prepare a Request for Expressions of Interest (RFEOI) to start selecting a private utility partner in a design build finance operate maintain (DBFOM) arrangement.
- Develop NEU connection guidelines to provide specifications to ensure new construction is compatible with the NEU.
- Implement a NEU service area bylaw which, would set the Moody Centre buildout in which new developments within that boundary would be required to connect to the NEU.
- Consult with instream developers on design interface between building and NEU. Â
More information is available in the full staff report.Â